QUESTION 1
On the CA Clarity PPM Global Header, what can you access through the Learn button?
A. CA Productivity Accelerator (CA PA) training modules
B. Collaborative communities
C. CA Clarity PPM bookshelf
D. CA Education website
Answer: A

QUESTION 2
When an incident is created, it is visible in one or more of the three tabs on the Incidents list page.
Which option correctly identifies the tabs that are visible?
A. Mine, Assigned, and Others
B. Open, Closed, and Resolved
C. Owned, Team, and Completed
D. Assigned to Me, Reported by Me, and Reported by Others
Answer: D

QUESTION 3
Line manager, Cliff Warner, shares resources with partner organizations. Cliff must have visibility
into the demand for those resources and must therefore have access to data across multiple
Organizational Breakdown Structures (OBSs). Development Manager, Maya Joshi, manages a
portfolio of investments for several business units and needs to make room for a new investment
request. To help them accomplish these tasks, which scenario type should Cliff and Maya create
in CA Clarity PPM?
A. Service Offering
B. Portfolio Analysis
C. Capacity Planning
D. Requirements Planning
Answer: C

QUESTION 4
You need to restrict project editing rights for project managers to the projects within their own team.
Which best practice should you follow?
A. Assign the Project – Edit or Project – Edit Management right (as appropriate), based on the
team’s project Organizational Breakdown Structure (OBS), to the selected users directly.
B. Create a security group with the team’s project OBS-based Project – Edit Management right
and associate users to that group.
C. Create a security group with the Global Project – Edit Management right and associate users to
that group.
D. Assign the Global Project – Edit right to the selected users directly.
Answer: B

QUESTION 5
You are both the project manager and the collaboration manager for a large implementation
project. You will use action items in the system to manage items on the project. To whom can
action items on a project be assigned?
A. Any participant
B. Any staff member
C. Only the project manager
D. Only the collaboration manager
Answer: A

…go to http://www.lead2pass.com/cat-241.html to download the full version Q&As.

         

Why Choose Lead2pass?

If you want to pass the exam successfully in first attempt you have to choose the best IT study material provider, in my opinion, Lead2pass is one of the best way to prepare for the exam.

Lead2pass Testking Pass4sure Actualtests Others
$99.99 $124.99 $125.99 $189 $29.99-$49.99
Up-to-Dated
Real Questions
Error Correction
Printable PDF
Premium VCE
VCE Simulator
One Time Purchase
Instant Download
Unlimited Install
100% Pass Guarantee
100% Money Back

Comments are closed.